39A Rehabilitation of Master Lift Station

Project Location: Manatee County, FL
Project Type: Public Utilities
Client: Manatee County – Public Works Department
Total Contract: $500K+

Prime Contractor on the master pump station facility for Manatee County Public Works, Florida. RTD contract work consisted of removal and replacement of existing liner system, repair all concrete damage under liner, furnish and install new explosion proof LED lights, 316 SS channel stop gates, fiberglass safety handrail and grating meeting OSHA requirements and under s strict bypassing operation. Project hi-lights include;

  • Bypass pumping system
  • Wetwell cleaning, demolition of existing protective liner system, concrete repairs
  • Install new concrete surfacing and new spray liner
  • New Stop Gates
  • New Handrail system and grating system with associated angle and supports
  • New wetwell access door and frame
  • New explosion proof LED lights

RTD self-performed 60% of all the work including all formwork, concrete work, bypass system, excavation & backfills, yard piping, FRP handrail and grating installation.